**The due date for this solicitation has passed**
CONSTRUCTION OF THE NORTH GATE BOULEVARD / STRUTHERS ROAD DRAINAGE AND PWQ POND PROJECT
Solicitation #
25-076
Status:
Awarded
Type:
IFB
Department:
Public Works
Open Date:
08/06/2025
Due Date:
09/03/2025
2:00 PM MST
2:00 PM MST
Award Date:
10/07/2025
Award:
Awarded to Amrize West Central Inc. for $3,474,562
25-076 IFB North Gate Boulevard Struthers Road Drainage and PWQ PondAttachments
25-076 IFB Final Award Notice - Amrize
07. North Gate-Struthers - Draft Environmental Assessment
25-076 IFB Notice of Intent to Award - Amrize West Central
25-076 IFB Submittal Log
01. North Gate - Struthers Bid Form
02. North Gate-Struthers - Final Plan Set
03. North Gate-Struthers - Proj Special & Std Special Provisions
04. North Gate-Struthers - Geotech Report
05. North Gate-Struthers - Drainage Report
06. Nationwide Permit (NWP) 43 Verification Letter & USFWS Biological Opinion
08. North Gate-Struthers - Environmental Assessment FONSI-FONPA
09. North Gate-Struthers - License to Construct
10. North Gate-Struthers - Minimum Quality Control Testing Requirements
11. North Gate-Struthers - Grading Erosion Control & Stormwater Management Plan
12. Permanent Control Measure Applicability Form
13. Erosion Stormwater Quality Control Permit (ESQCP) Application
14. Construction General Permit - SWPPP Checklist
15. CDOT Form 205 - Sublet Permit Application
16. CDOT Form 605 - Contractors Performance Capability Stmt
17. CDOT Form 606 - Anti-Colusion Affidavit
18. CDOT Form 621 - Assignment of Antitrust Claims
19. CDOT Form 1337 - Contractor Commitment to Meet OJT
20. CDOT Form 1413 - Bidders List
21. CDOT Form 1414 - Anticipated DBE Participation Plan
22. CDOT Form 1415 - Commitment Confirmation
23. CDOT Form 1416 - Good Faith Effort Report
24. CDOT Form 1418 - Monthly Payment Summary
25. CDOT Form 1419 - DBE Participation Report
26. CDOT Form 1420 - DBE Participation Plan Modification
27. CDOT Form 1425 - Supplier List
28. FHWA 1273 Federal Aid Contract Provisions for Construction Contracts (Exhibit I)
29. Additional Federal Requirements (Exhibit J)
30. FFATA Supplemental Federal Provisions (Exhibit K)
31. OMB Uniform Guidance for Federal Awards (Exhibit M)
32. B2G - LCPtracker Setup InformationAddendum 1
25-076 IFB Addendum #1
25-076 IFB - Pre-Bid Slides
25-076 IFB Attachment B - Sample Trade Contractor Agreement
25-076 IFB Sign In Sheet< Back to Solicitations